Who handles your permit

For property inside incorporated Rocklin, permits go through the City of Rocklin Community Development Permit Center at 3970 Rocklin Road, Rocklin, CA 95677 — (916) 625-5120 — not Placer County. Submittals run through the city's eTRAKiT portal. Rocklin approves or denies a complete, qualifying permit-ready ADU application within 30 days; custom designs take longer once engineering, revisions, and utility coordination are counted.

What you can build

1,200 sq ftMax for a detached ADU under state law
16 ftHeight limit for most detached ADUs
4 ftMinimum side and rear setbacks, detached ADUs
30 daysDecision on complete, qualifying permit-ready applications
75%Plan check fee is generally 75% of the building permit fee
60 daysState deadline to act on a complete application

Rocklin's Permit-Ready ADU program

The city offers a "Permit-Ready ADU" program with pre-designed plans that shorten review time. But there's an important exclusion: properties in Wildland-Urban Interface, special flood hazard, or geologic hazard zones don't qualify for the expedited route — those timelines run longer. Given Rocklin's rolling terrain and hillside edges, check your parcel's hazard designations before counting on the fast track.

Fees follow valuation. Rocklin's permit costs are based on project valuation, with plan check generally at 75% of the building permit fee — so a larger or more elaborate ADU compounds in more than one place. The most cost-controlled route is typically a permit-ready plan under 750 sq ft on a straightforward parcel.

What goes into the submittal

Where applications usually get stuck

Not sure where to start? That's the part we do. We check your parcel's hazard designations, compare the permit-ready and custom paths, and manage the submittal and corrections — one point of contact.

Tell us what you need help with.

Not sure where to start? That's what we're here for.

Send your project

Erik — (916) 540-8960 · Vall — (916) 956-8106